The topside is located in the German part of the North Sea on a traditional four-legged jacket on 30 m of water about 40 km from the German coast. The substation has a capacity of 332 MW.

The topside weights 1930 tons and the jacket has a weight of 1790 tons. Gode Wind 1 is a classic design with two transformers and a helideck.

The wind farm covers 42 km2 and will consist of 54 wind turbines of 6 MW each. 