Snekkersten Waterworks

In collaboration with our team consisting of general contractor Krüger, Contractor C.C. Brun Entreprise and Gottlieb & Paludan won the turnkey tender for construction of a new waterworks in Snekkersten.

The process plant, housed in two cubic building bodies, is symmetrically constructed in two lines. Each with a capacity of 200 m3/hour. This is equivalent to having two waterworks, and provides great security of supply.

The two lines are exactly the same, and located in the same building. It provides an operational advantage in the form of reduced manpower time, simpler inspection procedure, and fewer costs for external service and spare parts.

The waterworks will have a total capacity of 400 m3/h distributed over 2 lines.

The building and process plant were planned in 2018 and completed in 2020.

Our role as advisor

  • Project planning of constructions, installations, etc.
  • Rain and waste water
  • Constructions
  • Sanitation
  • Water
  • Heat
  • Drainage installations
  • Ventilation
  • Energy and Bsim
  • El
  • Professional supervision
  • Engineering advice in relation to total contract

Additional Information

  • Involvement of user groups in planning, etc.
  • BR15 building class 2020
Contact
Eva Lemb

Eva Lemb